|
|
County of Clear Creek |
|
Post Office Box 2000 |
|
|
ROADWAY DESIGN AND |
Revision Dates
This revision was printed on January 6, 2006
| Chapter 1 - Introduction and General Provisions 1.1 Short Title
1.2 Purpose and Intent 1.3 Enactment Authority
1.4 Types of Roads
1.4.1 County Owned and Maintained Roads:
1.4.2 County Owned Roads, but Maintained by Others:
1.4.3
County Maintained Roads, but Owned by
Others:
1.4.4 Privately Owned and Maintained Roads:
1.5 Road Naming and Numbering 1.6 Application of Standards
1.7 Upgrading of Existing County Roads
1.7.1 Definition of Development:
1.7.2 Upgrading Needed to Accommodate New Development:
1.7.3 Upgrading Requested by Property Owners:
1.8 Construction of New Roads
1.8.1
New Roads to be Built by Developers:
1.8.2 New Roads to be Built by County:
1.8.3 New Roads to be Built as Private Roadway for Five or Fewer Homes:
1.9 Permits for Road and Bridge Construction Prior to performing any work within the County road right of way, applicants must obtain a Right-of-Way Permit from the Road and Bridge Department. The procedure for obtaining Right-of-Way Permits is contained in Section 5.3. 1.10 Road Vacations
1.11 County Road Declarations Chapter 2 - Road and Bridge Design Criteria
2.1 Purpose and Intent
2.2 Adopted Policy and Design Reference Manuals
2.3 Road Classifications
2.3.1 Principle Arterials:
2.3.2
Arterials: Through roads and connections carrying heavy traffic flow into and out of subdivisions and various sectors of the county. Primary roads can have either asphalt surface and/or gravel surface, and are graded and drained. Roads in this category carry school bus traffic and mail routes and receive first day snow removal service by the Road and Bridge Department.
2.3.3 Collectors: Graveled, graded and drained roadways which are connectors carrying traffic into and out of subdivisions and various sectors of the county. Secondary I roads are capable of carrying school bus traffic and mail routes at the approval of the BOCC only. Secondary I roads receive first day snow removal service from the Road and Bridge Department, unless existing conditions curtail secondary service in order to focus operations on Primary Roads.
2.3.4
Local Access Road: Graveled, graded and drained roadways that are not approved for school bus service or mail routes, services residential areas and carries traffic to collector roads. Secondary II roads receive second or third day snow removal service from the Road and Bridge Department.
2.3.5
Low Volume Road: Roads classified as Secondary III, are roads that do not meet vertical or horizontal alignment standards, have a twelve to fifteen foot driving surface, and do not allow for the safe passage of two vehicles. The driving surface is generally not covered with a classified aggregate base coarse. Roads with this classification which are maintained on a year round basis, can expect snow removal on the third or fourth day, and may not receive snow removal with each snowfall. Additionally, these roads may not receive road grading on a regular basis, and some roads in this classification may have a seasonal maintenance classification, which will show on the road list as (S) denoting no winter maintenance.
2.3.6 Primitive Road: Roads falling into this category have a wide variety of road surfaces and provide ingress / egress for the traveling public. These roads include: roads which are declared public highways pursuant to CRS 43-2-201, R-98-181 by the BOCC and platted dedicated roadways in existing subdivisions which do not meet road design specifications. These roads are open and public roadways but are not included in the Road Mileage Tax System of the state of Colorado. Most of these roads are traversable by four-wheel drive vehicles only. These roads receive no snow removal, but may be periodically repaired by the Road and Bridge Department at the direction of the BOCC.
2.4 Road Design
2.4.1
Future Planning: A. Design Period: Roadway Design will be based on the projected
needs twenty (20) years after construction.
2.4.2
General Design Elements: 1. Property owners at the far end of a one-way loop road tend to take short
cuts and drive the wrong way to reach their properties, thus increasing the
chances for accidents. F. Striping: All paved roads may be striped with appropriate centerline and shoulder stripes per the MUTCD or CDOT Standard S-627-1. This shall apply to collector and higher functional classification roads or as determined necessary by the Road and Bridge Supervisor. 2.4.3 Specific Design Elements: A. Alignment: 1. Horizontal Alignment: a. Stopping Sight Distance: Horizontal alignment mustprovide at least the minimum stopping sight distance for the design speed at all points. This includes visibility at intersections as well as around curves and roadside encroachments. The minimum stopping sight distance is the distance required by the driver of a vehicle traveling at the design speed to bring the vehicle to a stop after an object on the road becomes visible, using the AASHTO recommended deceleration rate of 11.2 ft/sec2. Stopping sight distance is calculated in accordance with the following formula, or Table 4, whichever is greater: Stopping Sight Distance
Where an object off the pavement restricts sight distance, the minimum radius of curvature is determined by the stopping sight distance, but in no case will it be less than as specified in Table 5. Offset clearance to achieve stopping sight distance on horizontal curves can be obtained from Table 4. The centerline of the inside lane is used, with the offset distance measured from the centerline of the inside lane to the obstruction. b. Passing Sight Distance: Passing sight distance is the minimum sight distance that must be available to enable the driver of one vehicle to pass another safely and comfortably without interfering with oncoming traffic traveling at the design speed. Two-lane roads should provide adequate passing zones. Required passing sight distances for given design speeds are stated in Table 4. c. Curvature:
Table 5 specifies the minimum centerline radius of
curvature for specific design speeds. This table is based on speed alone and
does not take into consideration sight distance factors. Every effort should be
made to exceed the minimum values. d. Curb Returns: Curb returns or pavement rounding radii
Additional right of way will be required to provide a minimum clear distance for fifteen (15) feet between the curb or edge of pavement and the right-of-way limit. e. Intersections: The minimum distance between
Distance is measured from the inside edge of each right of way.
2. Vertical Alignment: These distances will be measured from the intersection of the right-of-way lines. The maximum design grade should be used infrequently rather than as a value to be used in most cases.
b.
Exceptions to Maximum Grade: A local access or low-volume Minimum lengths of crest vertical curves are controlled by stopping sight distance requirements. The minimum length for sag and crest vertical curves will be determined by Table 4. Vertical curves that are long and flat may develop poor drainage and should therefore be avoided. Vertical curves are not required where the algebraic difference in grade is less than 0.2%
d.
Sight Distance: The grade line must meet sight distance 3. Switchbacks: A switchback is defined as a curve with a delta greater than 120 degrees and a radius less than 100 feet. a. Use of Switchbacks: Switchbacks will not be allowed on collector 4. Alignment Coordination: When vertical and horizontal curves are superimposed, the super-elevation may cause distortion in the outer pavement edges. Where this may be the case, edge of pavement profiles shall be plotted and smooth curves introduced to remove any irregularities. Sharp horizontal curves should not be introduced at or near a pronounced crest or sag. |
| B. Geometric Cross Sections: 1. Typical Sections: A typical section for each road classification is shown in Figures 1 through 6. 2. Travel Lane Width: The minimum travel lane width for arterial and collectors is 12 feet, for local access roads is 11 feet, and low-volume roads is 10 feet. 3. Crown Slope: On undivided roads in tangent alignment, the high point of the crown will be centered on the pavement and the pavement sloped toward the edges on a uniform grade. In mountainous terrain, roads will be sloped toward the cut side of the road on a 3% slope to alleviate surface erosions. On divided multilane roads on tangent alignment, each travel way will have a uniform cross-slope with the high point at the edge nearest the median. The crown slope shall not exceed the percentages shown in Table 6. 4. Super-elevation: To account for snow and ice conditions, which occur frequently in Clear Creek County, the maximum super-elevation will be limited to 0.08 feet per foot, (see Table 7). The axis of rotation of undivided roadways is usually the centerline. For curves following long, level tangents, the axis of rotation shall be taken at the inside edge of the pavement. The divided roads with wide medians, the axis of rotation shall be the inside edge of pavement. For divided roadways with narrow medians, each roadway shall be rotated about the edge adjoining the median strip. 5. Super-elevation Transition: Super-elevation transition is the progression of the roadway from the normal crown section to a fully super-elevated section. To meet the requirements of safety and comfort, the length required to effect the transition should be adequate for the likely travel speeds. Suggested minimum lengths are given in Table 7. It is recommended that 60 to 80 percent of the super-elevation runoff be on the tangent. 6. Spiral Curves: Where the alignment includes spiral curves, super-elevation is applied entirely on the easement curve. 7. Curve Widening: Curves will be widened on the inside radius to allow for vehicular off-tracking in accordance with the following formula:
8. Cul-De-Sac Streets; Turnarounds: Whenever possible roadway systems shall provide at least two access points to lots platted for development. Using cul-de-sac streets shall be avoided. Where cul-de-sac streets are the only alternative, turnarounds shall be provided. Bulb type turnarounds shall have a minimum road surface 64 feet in diameter and a minimum right of way of 90 feet in diameter. An alternative to the bulb type turnaround is the use of a hammerhead turnaround. Figure 7 illustrates three acceptable hammerhead configurations. Roads ending in turnarounds greater than 600 feet in length shall provide wildfire mitigation such as: fire cistern storage, fuel breaks, and tree thinning as determined by the Clear Creek Fire Authority or the Evergreen Fire Protection District. Snow storage shall be provided as shown in Figure 7 to keep turnarounds cleared. Dead end roads that do not have turnarounds are not allowed. C. Structural Sections:
a. Traffic Index: The effect of traffic and weather on a roadway over
its design life is expressed by the traffic index (TI).
Table 8 shows the
minimum traffic index values for different road classifications. These minimums
may be proposed to be increased by the County Road and Bridge Supervisor and
approved by the BOCC if existing or future traffic warrants. D. Drainage: 1. General: The primary objective of drainage design is protection of
County roads and property while minimizing the possible flood damage to
surrounding properties and structures. It should be emphasized that a good
drainage is one of the most important factors in road design. It preserves the
appearance as well as the level of service of the road while minimizing
maintenance costs. Culverts under all roads shall be designed to accommodate a 25 year frequency storm run-off utilizing the maximum available head. The maximum available head shall be determined by the uppermost ponding elevation chosen to prevent flood damage to upstream properties. Inlets and other facilities draining the road surface shall accommodate the 25 year frequency storm runoff. All roads shall remain free of ponding. All drainage installations shall be designed to permit free, unobstructed passage of debris and silt or provide for their deflection and/or collection at a point upstream that will not create an expensive maintenance problem. Settlement basins shall be provided when a silting problem may exist downstream. Modification of natural channels or transferring runoff from one basin to another is not permitted except where no reasonable alternative exists and where the proposal has been reviewed and approved by the County Road and Bridge Supervisor and/or the BOCC. A recurring problem on Clear Creek County roads is ice build up in winters of little snow. Drainage design shall anticipate areas of potential ice build up. French drains that accommodate any off right-of-way drainage problem shall be designed to provide a minimum of 50 feet of overland sheet flow before reaching any roadside ditch. 2. Storm Runoff Estimates: The following methods may be used for estimating peak flows: a. Runoff from stream flow records.
The Rational method should only be used on areas of less than one hundred and sixty (160) acres. 3. Culverts: Culverts shall be located at each natural draw or water course as conditions warrant to prevent excessive accumulation of flow in roadside ditches or along the toe of slopes. Draws and water courses shall be cleared of debris for a distance of 100 feet upstream from all culvert inlets. Inverts at the inlet shall be slightly elevated above the normal flow line in steep or natural draws to avoid plugging by debris. Inlets shall not be elevated in those instances where ponding or accumulation of backwater curves would be objectionable (stagnation, irrigation ditches, etc.). The culvert shall slope downward in the direction of natural flow and be designed to be self-cleaning whenever possible. The outlet shall be designed not to discharge on unprotected fills or unstable material or at adverse angles to streams or open channels. Headwall, rip-rap or other means of protection are required at inlets or outlets where erosion might occur. Velocities of flow in culverts shall be calculated using acceptable design charts and formulas. Where the Manning-Equation is used, the following "n" values will apply:
Corrugated metal pipe, reinforced concrete pipe, high density polyethylene
pipe or an approved equal as specified by the Road and Bridge Supervisor shall
be used. Steel pipe shall be asphalt coated where soils are corrosive or other
conditions exist that may attack steel. Aluminum or other pipe materials are not
permissible for road culverts. Clean out access shall be provided at least every 200 feet for pipes 24 inches in diameter or less and at least every 400 feet for larger pipes. Clean out access shall also be provided at each angle point and at each change in grade. 4. Open Channels and Ditches: Channels and ditches shall be designed to avoid roadside safety hazards. The minimum flow line slope shall be 1.0 %. Maximum slopes shall be controlled by the maximum permissible velocities given in Table 11. Manning's equation shall be used to estimate velocities.
Where the materials channel is compromised of a combination of the materials given in Table 10, the maximum permissible velocity elected should prevent undue scouring of the finer materials silting downstream. 5. Subsurface Drainage: Sub-grades subject to poor drainage, underground seepage or a high water table shall be adequately drained for roadbed stabilization. Drains shall be installed to prevent high ground-water level from coming within four feet of the roadway pavement. Perforated pipe shall be used to carry away collected water. French drains which contain no pipe and are not wrapped with geotextile fabric are unacceptable. 6. Inlet Structures: Curb openings with protection bars are preferred. Other designs will be permitted on approval by the County Road and Bridge Supervisor. Grates are not permitted where pedestrians, bicycles or debris-laden flows are anticipated. E. Side Slopes: Transition slopes shall be provided between adjoining cuts and fills and shall be designed for pleasing appearance. Where cut or fill slopes intersect the original ground surface, the cross section shall be rounded to blend the slope into the natural ground surface. Where the slopes of the original ground approach 1.5:1, the embankment shall be contained with a suitable retaining wall to avoid long fill slopes. Side slopes in rock will be based on the stability of the formation. Retaining walls on the uphill side shall be a minimum of five (5) feet from the centerline of the adjacent drainage ditch. Benching of side slopes should be used sparingly and only where they are justified by sound engineering reasons, including the following:
Side Slopes that are steeper than 1.5:1 (H:V) shall be contained with a suitable retaining wall designed be a Colorado Registered Professional Engineer. Side Slopes in rock may be as steep as 0.5:1 (H:V) in competent formations when determined stable by a Colorado Registered Professional Engineer qualified in soil analysis. F. Sidewalks: 2.4.4 Payment of Costs for New Road Construction A. Developer Responsibility: B. Payback Agreements:
2.5.1 Design Standards:
A. Serving New Developments:
2. Payment of Costs: The developer shall be responsible for all costs
incurred to upgrade existing County roads.
2.6
Bridge Design The waterway area shall accommodate a 100 year flood event. Where flood studies from the U.S. Army Corp of Engineers or the Federal Emergency Management Agency are available, bridges shall be designed to accommodate the "Standard Project Flood". A minimum of one foot freeboard is required. Additional freeboard shall be required when debris laden flows are anticipated. Refer to the 1987 Clear Creek County Flood Plain Regulations.
2.6.2 Payment of Bridge Construction Costs:
2.7
Traffic Safety A. Design and Placement on Roadways: 1. When guardrail is used in conjunction with roadside curbs, the face of the
guardrail shall be flush with the face of the curb regardless of shoulder width.
This is to prevent the takeoff ramp effect which may overturn a vehicle. When no
curb is present, the face of the guardrail shall be flush with the edge of the
shoulder.
3. Whether on curves or tangents, consideration should be given to the
installation of guardrails if there is a history of roadway accidents or if
unusually high embankments or steep terrain give motorists a feeling of
insecurity.
B. Guardrail at Bridge Approaches:
2.7.2
Traffic Control Devices:
2.7.3
Sight Distance Triangle:
Examples of several typical combinations are provided in Figure 10. The area enclosed by the three sides of the triangle shall form an imaginary plane. The angle of the edge of this plane which lies along a right-of-way line shall be equal to the height of the corresponding point along the curb, or if there is no curb, to the elevation of the corresponding point along the centerline of the road. No landscape materials, earth berming, signs, structures, or other visual obstructions shall be allowed between three and one half (3-1/2) feet and seven (7) vertical feet above the surface of this plane. This regulation is not intended to prohibit the planting of trees or retention of existing trees in the sight distance triangle, if they are pruned so branches are higher than seven (7) feet. Installation of traffic control signs or signals and street lights are exempt from this regulation. B. Incorporation requirements for Sight Distance Triangles into
Subdivision Design: C. Enforcing Requirements When Building Permits are Issued: D. Continuing Enforcement of Requirement: 1. Determining whether the visual obstruction is within the sight triangle
for an intersection, and if it is on public or private property.
a. If the obstruction is a permanent structure which was built prior to the
effective date of this regulation, or was granted a variance as provided in the
Clear Creek County Zoning Regulations, the property owner shall not be required
to remove the structure. If the property owner does not comply within 30 days, further enforcement action shall be taken as provided in Chapter 8 of these regulations.
2.7.4 Above Ground Utility Location:
2.7.5
Rural Free Delivery Multi Box Modules: 1. The Postal Service will provide delivery service to the area proposed. Once a site, meeting these criteria, has been located the proponents shall stake the proposed location of the module and the edge of the right of way. The right of way shall be staked for a distance of fifty (50) feet on either side of the proposed location of the module. Upon completion of the staking, the Road and Bridge Department and the Postmaster shall inspect the proposed site to insure all the site requirements are met before giving preliminary approval. After preliminary approval, staff shall notify all property owners within a minimum of three hundred (300) feet of the proposed site and inform them of the request and allow them fourteen (14) days to appeal the staff decision. If no appeals are received in the allotted time, staff will inform the proponents by written notice that they can begin construction once they obtain a right-of-way permit (Chapter 5, Section 5.3). In the event of an appeal, staff will schedule a hearing with the BOCC within thirty (30) days of receiving the appeal request. Property owners originally noticed for the proposed site will be re-noticed for the appeal. Proponents and opponents will have the opportunity to state their arguments supporting their respective positions. The BOCC decision will be final. After construction has been completed, a final inspection shall be done to insure the module was properly installed and the pull off was constructed to County standards. All deficiencies shall be corrected before final approval can be given to start mail service. The homeowners association or other designated group from the subdivision shall be responsible for all costs associated with the construction of the module and pull off and all future maintenance including snow removal of the pull off area. Individual mail boxes on individual properties will not be allowed in new areas requesting rural mail deliver Individual mail box installations, on public roadways in Clear Creek County, shall be made in a cantilever style to prevent blockage or obstructing maintenance operations of the drainage channels. Boxes must be installed between forty two (42) and forty eight (48) inches above the road surface and positioned so the opening or front of the box is at the outer edge of the shoulder (edge closest to the ditch). Posts must not be set in the ditch or on the roadway side of the ditch to allow for maintenance operations. It is the responsibility of the property owner to maintain mail boxes and to clear snow from around mail boxes to allow for mail delivery. (See Figure 12) 2.8 Grading Permits and Parking Areas
2.8.1 Requirement for Grading Permit:
2.8.2
Standards for Parking Areas:
2.9
Landscaping and Erosion Control Erosion Control and Environmental Mitigation Efforts for Road Construction Chapter 3 - Road and Bridge Construction Specifications
3.1 Purpose and Intent 3.2 Closing of Streets and Roads
3.2.1 Notice and Operation of Street Closure: 1. Submit a traffic control plan for review and approval by the County Road
and Bridge Department a minimum of six (6) working days prior to closing the
road. See Chapter 5 Section 5.4.3 for emergency situations.
3.3.1 Permits Required for Road Construction/Grading: Whenever road grading of an existing or historic access road is proposed the individual responsible for the construction must obtain approval for a grading permit from the Road and Bridge Department prior to commencing construction. Grading is defined as any alteration of the existing topography. In general, grading permits are required for minor changes of an existing public road’s horizontal or vertical alignment, or for reshaping an existing public road to maintain driving surface and drainage infrastructure. A. The submittal requirements and procedure for obtaining road construction permits are as follows: 1. No permit will be issued without the submittal of two (2) completed
application forms (no photocopies accepted) along with two (2) copies of the
appropriate engineer drawings and specifications. B. The submittal requirements and procedure for obtaining grading permits are stated as follows: 1. Two (2) copies of the site plan must accompany two (2) original copies of the signed application showing with reasonable accuracy the nature and extent of the proposed work. The site plans need to show the following detail:
2. The Road and Bridge Supervisor or his designee will require testing by a
soils engineer if he/she believes that hazardous geological factors may exist.
If a soils engineer finds that hazardous factors do exist, you will be required
to conform to the engineer’s plan. C. A Performance Guarantee is required for Road Construction and Grading Permits in amounts as set forth in the Permit Fee Schedule. These amounts shall be based on contract prices for performing such work, as specified and approved by the Road and Bridge Supervisor and amended in the fee schedule as necessary. The Performance Guarantee is to ensure completion of the work in accordance with approved plans and without damage to the road or right of way. 1. All Performance Guarantees will be (i) in cash, together with an executed
Security Agreement, or (ii) by Letter of Credit issued by a bank physically
doing business in the state of Colorado, drawable in the state, and in a form
acceptable to the County Attorney.
3.3.2 Construction Testing: A. Sampling of Materials: |
| A.
Utilities Protection: The developer and contractor shall at all times take proper precautions to assure the protection of utilities, service lines, or other public or private installations and shall be responsible for the repair of any damage. The developer or contractor shall notify the utilities forty-eight (48) hours before excavation begins, so the utilities can locate the services. B. Grubbing: All large rocks, brush debris, structures and all other unsuitable material shall be cleared to a depth of at least twelve (12) inches below subgrade or as directed by the County Road and Bridge Supervisor and be replaced with suitable material. Locating suitable disposal sites shall be the responsibility of the contractor or developer subject to County approval. Trees, except those designated to be saved, and all stumps shall be removed to a depth of at least eighteen (18) inches below the finished subgrade elevation. All trees designated to be saved shall be protected during clearing and subsequent construction operations. Suitable material removed from the excavation may be used in so far as practical, in the formation of embankments, backfilling and for such other purposes. Embankment construction consists of constructing roadway embankments, including preparation of the areas upon which they are to be placed; constructing dikes within or outside the right of way; placing and compacting of approved material within roadway areas where unsuitable material has been removed; and placing and compacting of embankment material in holes, pits, and other depressions within the roadway area. Only approved materials shall be used in the construction of embankments, and backfills. A. Benching:
3.3.5
Trench Excavation: A. Trench Widths:
1.
Initial Backfill: To aid curing, no more than eight inches of loose
backfill shall be placed over concrete after the concrete has reached its
initial set. F. Compacted Backfill:
3.3.6
Culverts: A. Materials: 1. Circular Pipe: Corrugated metal pipe shall be AASHTO M36-78 and galvanized with 2-2/3" x 1/2" corrugations. The corrugations may be
annular or spiral with annular ends. B. Handling: a. Pipe: The pipe shall be installed in accordance with the
details indicated on Figure 20 and
21 and the applicable portions of the evacuation
section. The pipe shall be protected from lateral displacement by means of a
pipe embedding material as specified for trench backfill. The minimum cover for
corrugated metal pipe is 12 inches. 2. Use of Culverts at Access Point of Roads: Driveways or road connections to a County road shall not be constructed in such a way as to impede the normal flow of drainage in roadside ditches, culverts, underdrains, bridges or other drainage works, or to cause such drainage to flow onto or across the driving surface of a County road. In the event that such an impediment results in damage to a County road, the Road and Bridge Supervisor will remove the impediment and bill the property owner for the costs of repairs to the road, including labor, equipment and material. In certain instances, a culvert may not be required by virtue of the topography. In that event, a written waiver must be obtained from the Road and Bridge Department. Such a waiver does not constitute a waiver of the permit fee, inspection of the access or any requirement of the access.
3.3.7 Subgrade: A. Subgrade Specifications:
3.3.8
Gravel Roads: A. Gravel Specifications: A. Subbase Specifications: B. Base Course: C. Asphalt Concrete Pavement: a. Crushed Gravel: The gravel to be used shall consist of clean, hard, durable particles which have been crushed to the gradations
specified on Table 15. Of the particles retained on the No. 4 sieve, at least
60% by weight shall have one or more fractured faces. The crushed gravel when
tested in accordance with AASHTO Standard Test Designation T-96, shall have no
more than 50% wear and shall show no detrimental amount of stripping when
tested. Determination of the effect of water on the cohesion (stripping
resistance) of asphaltic concrete composed of the proposed mineral aggregates
shall be made in conformance with AASHTO Standard Test Designation T-165-77 with
a minimum dry strength of 200 psi with a minimum retained strength of 75% of the
dry strength.
2. Establishing Job Mix Formula: The job mix formula for each mixture shall establish a single percentage of aggregate passing each required sieve size, a single percentage of bituminous material to be added to the aggregate and a single temperature for the mixture at the discharge point of the plant. After the job mix formula is established, all mixtures furnished for the project shall conform to the following ranges of tolerances:
3. Sampling and Testing: All sampling and testing of materials shall be done in accordance with the latest methods of the AASHTO. The County Road and Bridge Supervisor shall be supplied with a Certificate of Compliance with the Colorado Department of Transportation Specifications before any asphalt is placed. D. Construction of Asphalt Roads: E. Drainage Pans:
3.4
Landscaping Installation Chapter 4 - Driveway Permit Requirements
4.1 Purpose and Intent
4.2 Permits and Performance Guarantees 4.3 Procedures/Requirements for Issuance of Driveway Permits
4.3.1 Submittal Requirements for Driveway Permits:
4.3.2 Action on Driveway Permits: |
|
4.3.3
Construction Specifications for Driveway Work: All work undertaken to connect driveways to existing County roadways shall conform to the Road and Bridge Design and Construction Standards contained in these regulations.
4.3.4 Construction Schedule for Driveway Work:
4.4 Supervision of Driveway Work
4.5 Inspection and Testing of Driveway Work Any work or material which does not conform to these regulations, any pavement failures or broken asphalt, damaged signs or fencing, and remaining debris either in the roadway or adjacent property, or improper drainage shall be brought to the attention of the permit applicant both verbally and in writing. Any work in which untested or unaccepted materials are used shall be ordered removed and replaced at the permit applicant’s expense. Any required corrective work shall be made at the permit applicant’s expense and shall be done to the satisfaction of the Site Development Department. If immediate corrections are not made, further project construction shall be stopped. In determining whether or not the driveway work done by the permit applicant is acceptable, the Site Development Department may consult with the Road and Bridge Department. If a determination is made that testing is required, the number and location of the tests shall be determined by the Site Development Department. If the Site Development Department determines testing by an independent lab is necessary, the cost of such testing shall be paid by the permit applicant.
4.6 Responsibility for Rework on Driveway Connections 4.7 Driveways and Parking Areas
4.7.1 Requirement for Driveway Permit:
4.7.2 Requirement for Grading Permit:
4.7.3 Standards for Driveway Design: A. Location of Driveways Relative to Intersections: Where the driveway connects to a local access or low-volume road, a minimum distance of 50 feet from curve return to edge of right of way at the intersection shall be maintained. Where a driveway connects to a collector or larger road, a minimum distance consisting of the left turn stacking distance plus 20 feet as measured from curve return to curve return, shall be maintained (see Figure 16). The left turn stacking distance shall be determined by the Road and Bridge Department based on available data from an acceptable traffic study. If a traffic study is not available, or data provided is incomplete, the Road and Bridge Department shall estimate the length of the left turn stacking distance using the following formula:
The Road and Bridge Department may make adjustments in the factors used in this formula for a typical situation. Examples of such situations include the intersection of low-volume roads with very high-volume roads, or where adjacent land uses cause traffic patterns to be skewed. If an applicant disagrees with the left turn stacking distance determined by the Road and Bridge Department, they may purpose a different distance if substantiated by a traffic study that is acceptable to the BOCC. B. Spacing of Driveways: E. Driveway
Cross Section: Q. Maintenance: R. Deviation from the Standards: A. Parking Index:
4.8
Landscaping and Erosion Control Erosion Control and Environmental Mitigation Efforts for Driveway
Construction: Chapter 5 - Right-of-Way Permit Requirements
5.1
Purpose and Intent
5.2
Requirements for Financial Guarantees
5.3
Procedures/Requirements for Issuance of Right-of-Way Permits
5.3.1
Submittal Requirements for Right-of-Way Permits:
J. Owners of property or businesses abutting the utility projects shall be advised of permit applications, by the applicant, that may affect their convenience and economic well-being (See Section 3.2).
5.3.2
Action on Right-of-Way Permits: Approval of a Right-of-Way Permit may be accompanied by any conditions deemed reasonable by the Road and Bridge Department to insure protection of health, safety, and welfare and compliance with these regulations. The Right-of-Way Permit must be signed by the Road and Bridge Supervisor or his designee for it to be approved. Whenever a driveway permit is needed in conjunction with right-of-way work, the Right-of-Way Permit shall not be issued until approval is granted for the needed driveway permit. During the period of each October 31st through May 31st of succeeding year non-emergency permits for installation required to be done during that period to comply with PUC laws, rules and regulations, will be approved for boring or open trench work only if above ground temporary installation is not suitable and flowable fill shall be the only approved backfill.
5.3.3
Construction Specifications and Schedule for Right-Of-Way Work: 5.3.4
Emergencies: 5.3.5
Expiration of Right-of-Way Permits:
5.4
Posting Right-of-Way Permits
5.5
Procedures for Road Closures During Right-of-Way Work
5.5.1
Submittal of Plans and Schedule for Closures:
5.5.2
Notification of Closures:
5.5.3
Time of Closures; Detours:
5.6
Protection of Public Safety and Convenience
5.7
Construction Procedures for Right-of-Way Work
5.7.1
Compliance with Safety Standards:
5.7.2
Staging of Installations:
5.7.3
Installation of Utilities: A. Underground Utilities:
5.7.4
Trenching, Backfill and Reconstruction of Road Surfaces:
5.8
Inspection and Testing of Right-of-Way Work Any work or material which does not conform to these regulations, any pavement failures or broken asphalt, damaged signs or fencing, any remaining debris either in the roadway or adjacent property, or improper drainage, shall be brought to the attention of the permit applicant both verbally and in writing. Any work in which untested or unaccepted materials are used shall be ordered removed and replaced at the permit applicant’s expense. If immediate corrections are not made, further project construction shall be stopped. In determining whether or not right-of-way work done by the permit applicant complies with these regulations, the Road and Bridge Department may consult with an engineer at the permit applicant’s expense. If it is decided testing is required to ascertain compliance, the most recent standard methods of AASHTO or ASTM shall be used and conducted by an independent testing firm at the permit applicant’s expense. If the permit applicant maintains his own testing equipment and qualified personnel, the requirement for an independent testing firm may be waived by the Road and Bridge Supervisor. Copies of test data shall be furnished to the Road and Bridge Department in a timely manner.
5.9
Responsibility for Corrective Work Upon Completion of Right-Of-Way Work
5.10
Guarantee Period for Right-of-Way Work
5.11
Changes Affecting Utilities Chapter 6 - Road Acceptance and Maintenance
6.1 Purpose and Intent In order for maintenance to be done on an efficient basis, roads must be constructed to certain standards of geometric alignment, materials quality and construction quality as described in these regulations. Before the County will maintain roads built by developers or owned and maintained by private property owners, they must petition the BOCC to accept the roads for maintenance. A minimum of one (1) year will elapse between the time the petition is reviewed and if approved probationary maintenance can begin. This period of time is due to the budget process time needed to insure funds are available to maintain the road. This section outlines the acceptance procedure and the conditions that must be met for approval. This standard supersedes Resolution 98-171.
6.2 Maintenance Classifications
6.2.1 Full:
6.2.2 Probationary:
6.2.3 Provisional:
6.2.4 No Maintenance:
6.3 Assumption of Road Maintenance 1. The revenues received and the costs incurred to maintain the road. The County shall review each road individually within a development to determine if that road should receive County maintenance.
6.4 Provisions for Private Maintenance They shall also require through covenants or deed restrictions that all property owners within their development join this organization and assume their share of its financial obligations. Where a new organization must be formed because no existing organization is in close proximity, the developer shall form a metropolitan district, special district, homeowners association or other appropriate organization approved by the County for this purpose.
6.5 Acceptance of Private Right-Of-Way Roads for Maintenance
6.5.1 Filing Request for County Acceptance:
6.5.2
Staff Evaluation and Recommendation: If site conditions are so limiting that they make it impractical or impossible to bring existing road conditions up to these standards the petitioners will present written argument to the BOCC as to why the road should be excepted from the recommended standard and how safety issues will be mitigated. The Road and Bridge Supervisor and/or the Site Development Inspector will provide written comment to the BOCC as to the reasonableness of the request, any potential impacts that the exception might create for the County and a recommendation.
6.5.3 BOCC Action on Request:
6.5.4 Final Acceptance:
6.6 Acceptance Procedure for Roads Constructed by Developers
6.6.1
Design Review:
6.6.2 Inspections:
A final inspection shall be conducted after the completion of all improvements. The final inspection shall occur between May 1st and October 31st. Roads must comply with the design criteria and construction standards in these regulations, and with any approved plans. If the inspection discloses any work, in whole or in part, as unsatisfactory, the Road and Bridge Supervisor shall follow the procedure stated in Section 3.3.2.
6.6.3 Filing Request for County Acceptance:
6.6.4 Staff Evaluation and Recommendation:
6.6.5 BOCC Action on Request for Acceptance:
6.6.6 Guarantee Period After Probationary Acceptance:
6.6.7 Final Acceptance:
6.7 Acceptance Procedure for Roads Constructed Through Local
Improvement Districts
6.7.1 Design and Construction Standards for Local Improvement
Districts:
6.7.2 Construction Supervision for Local Improvement Districts:
6.7.3 Staff Evaluation and Recommendation:
6.7.4 BOCC Action on Request for Acceptance:
6.8 Responsibilities for Road Maintenance
6.8.1 Providing for Parking:
6.8.2 Providing for Drainage: Water which flows out of driveways must be diverted to ditches. Damage to roadways caused by such water is similarly the responsibility of the owner and repair costs will be billed.
6.8.3 Keeping Right of Way Clear:
6.8.4 Repairing Damage: Chapter 7 - Deviations From Design and Construction Standards
7.1
Exceptions to Design and Construction Standards A. Where, by reason of exceptional topographic or physical conditions or
other extraordinary and exceptional situations or conditions, the strict
application of these regulations would result in peculiar and exceptional
practical difficulties to, or exceptional and undue hardship upon, an individual
proposing to construct a road or bridge provided the conditions in Section
7.1.C
are met.
C. Deviations from standards that are necessary due to difficulties or hardships described in Section 7.1.A and 7.1.B may be granted provided relief will not result in substantial detriment to public health, safety and welfare, substantial impairment of the road design and construction standards, or the granting of any special privilege or use. Prior to the BOCC taking action, the BOCC shall refer any deviation from standards request to the appropriate fire district and other interested agencies for comment. Chapter 8 - Enforcement of Design and Construction Standards
8.1
Enforcement When Subdividing Property A. Subdivision improvements agreement (SIA) to construct any required public improvements shown in the final plat documents together with collateral that is sufficient, in the judgment of the BOCC, to make reasonable provision for the completion of said improvements in accordance with design and time specifications. B. Other agreements or contracts setting forth the plan, method and parties responsible for the construction of any required public improvements shown in the final plat documents which, in the judgment of the BOCC, will make reasonable provisions for the completion of said improvements in accordance with design and time specifications. Any roads or bridges required to be constructed, improved or upgraded shall meet the design and construction standards contained in these regulations, or as allowed by any deviation from standards approved by the BOCC. The subdivider shall post a financial guarantee acceptable to the County Attorney to insure construction of these improvements prior to the issuance of the "Certificate of Compliance" and the start of construction.
8.1.2
Use of Collateral: 8.1.3
Restrictions on Transfer of
Property:
8.2
Use of Property for Road and
Bridge Construction Any person, firm or corporation violating any portion of these regulation is guilty of misdemeanor and, upon conviction thereof, shall be punished by a fine of not more than one hundred dollars, or by imprisonment in the County Jail for not more than ten days, or by both such fine and imprisonment. Each day during which such illegal erection, construction, reconstruction, alteration, maintenance or use continues shall be deemed a separate offense (C.R.S. 30-28-124). The issuance of a building permit or a certificate of occupancy may be withheld for property unless the plans for the proposed erection, construction, reconstruction, alteration or use fully conform to these regulations or for property on which a violation of the provisions of these regulation exist, until such violation has been corrected to the satisfaction of the BOCC (C.R.S.30-28-14).
8.3
Issuance of Work Stoppage
Injunction
8.4
Effective Date Of Design and
Construction Standards Roads or bridges which have been approved as part of a subdivision or site plan prior to final approval of these regulations, and where construction is commenced prior to expiration of the final plat or site plan may be built in accordance with the design and specifications approved in conjunction with the plat or site plan. |